★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PMI-001 Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/PMI-001-dumps.html


With the help of Examcollection PMI-001 dumps, you can aquire a great end result merely that make a person complete PMI examination. In addition, should you unsuccessful in the PMI-001 examination for the first time of employing our products, just about all cash you spend will probably be return. You only need to send your PMI-001 statement records because the pdf file to us. After verifying your information, well return the money and also return it in your accounts at the earliest opportunity.

2021 Jun PMI-001 torrent

Q371. When does risk monitoring and control occur? 

A. At project initiation 

B. During work performance analysis 

C. Throughout the life of the project 

D. At project milestones 

Answer: C 


Q372. Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis? 

A. Initiating 

B. Monitoring and Controlling 

C. Planning 

D. Closing 

Answer: C 


Q373. Cost aggregation is typically performed by aggregating work packages in accordance with the: 

A. Program evaluation and review technique (PERT). 

B. Cost of quality (COQ). 

C. Rough order of magnitude (ROM). 

D. Work breakdown structure (WBS). 

Answer: D 


Q374. In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements? 

A. Technical approach 

B. Technical capability 

C. Business size and type 

D. Production capacity and interest 

Answer: A 


Q375. Which is a tool used in monitoring and controlling project work? 

A. Work performance information 

B. Project management information system (PMIS) 

C. Activity duration estimates 

D. Scheduled network analysis 

Answer: B 


PMI-001 free practice exam

Down to date PMI-001 practice test:

Q376. The zero duration of milestones in project planning occurs because milestones: 

A. Are unpredictable and challenge the Plan Schedule Management process. 

B. Occur at random times in the project plans. 

C. Represent a moment in time such as a significant project point or event. 

D. Represent both significant and insignificant points in the project and are difficult to anticipate. 

Answer: C 


Q377. Which quality planning tools and techniques are used to visually identify logical groupings based on natural relationships? 

A. Force field diagrams 

B. Cause-and-effect diagrams 

C. Affinity diagrams 

D. Nominal group techniques 

Answer: C 


Q378. The PV is $1000, EV is $2000, and AC is $1500. What is CPI? 

A. 1.33 

B. 2 

C. 0.75 

D. 0.5 

Answer: A 


Q379. Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic? 

A. Internal 

B. External 

C. Discretionary 

D. Mandatory 

Answer: C 


Q380. When does the project team determine which dependencies are discretionary? 

A. Before the Define Activities process 

B. During the Define Activities process 

C. Before the Sequence Activities process 

D. During the Sequence Activities process 

Answer: D