★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PRINCE2-Foundation Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/PRINCE2-Foundation-dumps.html


Proper study guides for Up to date PRINCE2-Exams PRINCE2 Foundation exam certified begins with PRINCE2-Exams PRINCE2-Foundation preparation products which designed to deliver the Practical PRINCE2-Foundation questions by making you pass the PRINCE2-Foundation test at your first time. Try the free PRINCE2-Foundation demo right now.

2021 Oct prince2 foundation examination questions:

Q41. - (Topic 1) 

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance. 

A. quality 

B. supplier 

C. risk 

D. product 

Answer:


Q42. - (Topic 1) 

What takes place during the Closing a Project process? 

A. The post-project benefits reviews are performed 

B. Ownership of the project's products is transferred to the customer 

C. An End Stage Report is prepared for the final stage 

D. The project closure notification is reviewed and approved 

Answer:


Q43. - (Topic 2) 

How should the Team Manager report that tolerances are forecast to be exceeded? A. Create an Exception Report 

B. Create a Highlight Report 

C. Raise an issue 

D. Grant a concession 

Answer:


Q44. - (Topic 2) 

Which should be provided by a project mandate? 

A. Terms of reference 

B. Detailed Business Case 

C. Stage tolerances 

D. Initiation Stage Plan 

Answer:


Q45. - (Topic 2) 

Why is a Project Brief produced? 

A. To act as a trigger for the Starting up a Project process 

B. To record the strategies and management controls to be used by a project 

C. To provide a full and firm foundation for the initiation of a project 

D. To be used by the Project Board as a basis for reviewing the progress of a project 

Answer:


Updated prince2 foundation exam advice:

Q46. - (Topic 2) 

Which is a responsibility of a risk owner? 

A. Identify risks to the project that might occur in their department 

B. Own and authorize the use of the risk budget to fund risk responses 

C. Manage, monitor and control all aspects of an assigned risk 

D. Determine project risk appetite 

Answer:


Q47. - (Topic 1) 

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers? 

A. Create a separate Project Board to manage the supplier elements of the project 

B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages. 

C. Create user and supplier groups 

D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board 

Answer:


Q48. - (Topic 2) 

How many management stages should a PRINCE2 project consist of? 

A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project 

B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage 

C. Initiation stage and at least one other management stage to cover the remainder of the project 

D. Start up stage, initiation stage and a closing stage 

Answer:


Q49. - (Topic 1) 

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment? 

A. Specify the desired result 

B. Provide the resources and skills to deliver the desired result 

C. Ensure the technical integrity of a project 

D. Develop a project's products 

Answer:


Q50. - (Topic 2) 

Which statement describes the 'Implement' step within the recommended risk management procedure? 

A. Take planned action to respond to a risk 

B. Implement the responsibilities for risks defined in the Risk Management Strategy 

C. Assess the proximity of a risk 

D. Identify the level of risks that can be tolerated by the project 

Answer: