★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW 70-499 Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/70-499-dumps.html


Proper study guides for Renew Microsoft Recertification for MCSD: Application Lifecycle Management certified begins with Microsoft 70-499 preparation products which designed to deliver the Free 70-499 questions by making you pass the 70-499 test at your first time. Try the free 70-499 demo right now.

2021 Sep 70-499 brain dumps

Q111. - (Topic 2) 

You are using Microsoft Test Manager (MTM). 

You have a shared steps work item that you want to hide in the Shared Steps Manager. 

You need to ensure that only active shared steps work items are displayed. 

What should you do? 

A. Change the state of the shared steps work item to Closed, then customize the filter of the Shared Steps Manager view to display shared steps that have the status Active. 

B. Delete the shared steps work item from all test cases where it is used, then delete the shared steps work item from the Shared Steps Manager. 

C. For the shared steps work item, change the Show in Shared Step Manager setting to Do Not Show. 

D. Change the state of the shared steps work item to Removed. 

Answer: A 


Q112. - (Topic 1) 

Your team uses Microsoft Visual Studio Team Foundation Server (TFS) to manage software development processes that have multiple team projects associated to a single team project collection. 

You install a second TFS server in order to establish a test environment for future changes. 

You need to copy the contents of your team project collection to your new TFS installation. 

Which two actions should you perform first? Each correct answer presents part of the solution. 

A. Create a backup of the team project collection database. 

B. Configure your new TFS to use the same databases as your initial TFS. 

C. Attach the team project collection on the new server. 

D. Detach the team project collection from TFS. 

Answer: A,B 

Explanation: http://msdn.microsoft.com/en-us/library/ms404869.aspx 


Q113. - (Topic 1) 

Your client’s network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server installed at its main office. 

The network administrator at a remote office reports high WAN utilization. Users at the remote office report slow response times when downloading source code. 

You need to minimize WAN utilization and improve the response times for downloading source code. 

What should you do? 

A. Install TFS Server at the remote site and set up database synchronization between the existing TFS Server and the remote site. 

B. Install and configure TFS Proxy at the remote site. Point the TFS Proxy to the TFS server and point Team Explorer to the TFS Proxy. 

C. Install and configure IIS caching. Point Team Explorer to the IIS server. 

D. Install TFS Proxy at the remote site. Configure TFS Proxy to point to the TFS Server and configure each user’s Visual Studio Source Control to use the proxy server for file downloads. 

Answer: D 


Q114. - (Topic 2) 

You are a test developer using Microsoft Test Manager (MTM). 

An application that you are testing has gone through a design change. The test case now has five test steps that contain obsolete parameters. 

You need to completely remove these parameters, their data values, and their names, but keep the test steps intact. 

What should you do? 

A. Delete all of the data value iterations for the obsolete parameters by clicking Delete iteration in the Parameter Values pane. 

B. Delete the obsolete parameters from the test case by clicking Rename parameter in the Parameter Values pane and replace the name with a blank replacement value. 

C. Delete the test steps with the old parameters and insert a new test step in their place. 

D. Delete the obsolete parameters from the test case by clicking Delete parameter in the Parameter Values pane and remove the parameter name from the test steps. 

Answer: D 


Q115. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. Developers use Visual Studio 2012 to maintain a library of commercial .NET components provided for sale by your company. 

You release new versions quarterly and provide support for the four most recent versions. When issues are logged with previous versions it is time-consuming for your developers to locate and associate the correct version of debugging symbols and source code. 

You need to streamline the process for debugging prior versions of your library. 

What should you do? 

A. When it is time to deploy each quarterly update, copy the release binaries into version control. 

B. Within the build definition, set the Index Sources property to True and provide a path for the symbols. Add this path to the list of symbol file locations in Visual Studio when debugging that particular version. 

C. When it is time to deploy each quarterly update, label the source code with the version number being released. 

D. Enable IntelliTrace within Visual Studio. Within the build definition, set the IntelliTrace option to True. 

Answer: B 


70-499 free practice questions

Up to the immediate present 70-499 question:

Q116. - (Topic 3) 

You are utilizing the Microsoft Visual Studio Scrum 2.0 process template. 

Your development team uses the storyboard feature in Visual Studio 2012. 

You need to ensure that there is consistency of user interface between different features of the product. 

What should you do? 

A. Create a design guide document with images of sample standard layouts. Provide a copy of this document to all team members. 

B. Create custom storyboard shapes by using Microsoft PowerPoint that match your corporate standard user interface (UI) controls. Export these and make them available to the team as an import for use in all storyboards. 

C. Create custom storyboard shapes in PowerPoint that match your corporate standard UI controls. Save the results as a PowerPoint template in the SharePoint site associated with the Team project collection. Instruct team members to import the shapes. 

D. Create images of your UI controls as GIF/JPEG files that match your corporate standard UI controls. Export these and make them available to the team as an import for use in all storyboards. 

Answer: B 

201. - (Topic 3) 

You develop an n-tier application that includes the following components: 

.... 

Database 

Data access layer 

Business logic layer 

Presentation layer (website) 

The database has approximately 100 tables and stores large amounts of data. 

You need to select a unit testing strategy to verify the business logic layer. 

What should you do? 

A. 

Create a mock data access layer. 

Configure the business logic layer to use the mock data access layer. 

Write tests against the business logic layer. 

B. 

Create a mock data access layer. 

Write tests against the mock data access layer. 

C. 

Create a mock business logic layer and a test database. 

Configure the data access layer to target the test database. 

Write tests against the business logic layer. 

D. 

Create a test database from a backup of the live database. 

Configure the data access layer to target the test database. 

Write tests against the data access layer. 

Answer: A 


Q117. - (Topic 3) 

You are the product owner for a new application. You have the list of product backlog items (PBIs) with assigned business values for the first release of the application. You will be working with an established scrum master and development team. You know the team’s capacity and the planned sprint duration. 

You need to plan the release schedule based on your existing backlog. 

Which three actions should you and the team perform? (Each correct answer presents part of the solution. Choose three.) 

A. Ask the development team to decompose the PBIs into individual tasks and estimate hours. 

B. Ask the development team to provide high level estimates to complete each PBI. 

C. Assign the PBIs to different sprints to define the release. 

D. Use the TFS 2012 task board features. 

E. Schedule the release using the Iteration Planning workbook. 

F. Order the product backlog by business value. 

Answer: B,C,E 

Explanation: Not clear because according to Planning a release they say: 

Note Release planning is no longer an official event in Scrum. It’s assumed that every 

organization will do some level of release planning. As far as Scrum is concerned, keeping 

the Product Backlog healthy and estimated is the best input for accurate release planning. 

Professional Scrum Development with Microsoft Visual Studio 2012 p.160 


Q118. - (Topic 2) 

You are using Microsoft Test Manager (MTM). 

Your company has configured multiple test configurations. 

You need to set all active test configurations as the default for all new test plans. 

What should you do? 

A. Select the Active state option for each test configuration. 

B. Select the Default option for each test configuration. 

C. Select multiple test configurations from the test plan. 

D. Select the Assign to new test plans option for each test configuration. 

Answer: D 


Q119. - (Topic 3) 

Your development team uses the Microsoft Visual Studio Scrum 2.0 process template. You are the scrum master. 

The product owner has created product backlog items and assigned them to a release. 

You need to work with the development team to estimate when the release will be completed. 

Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.) 

A. Review the sprint backlog. 

B. Review the product backlog with the Forecast option set to on to determine if the release can be completed based on the team’s velocity. 

C. Have the team create tasks for each item in the product backlog and assign hour estimates to the task. 

D. Review the sprint burndown chart. 

E. Set each team member’s per day capacity. 

F. Establish a sprint duration and a sprint velocity. Create enough sprints to complete the release. 

G. Estimate effort for each item in the product backlog. 

Answer: B,F,G 

Explanation: By using the forecasting tool in Web Access, you can plan the number of Sprints it will take to complete a set of work. The forecasting tool is available only in the Product Backlog, not any of the Sprint Backlogs. Prior to being able to use the forecasting tool, your Product Backlog must have PBI and Bug work items already created with the effort specified. 

You can turn on forecasting by clicking the Off hyperlink next to Forecast on the right side of the backlog page. The first time you do this, Web Access prompts you for the Velocity. Using your Development Team’s Velocity, Web Access will add a Forecast column and horizontal lines to the Product Backlog. In the Forecast column, it will display the Sprint that it predicts the PBI or Bug work item will be developed in. 

Professional Scrum Development with Microsoft Visual Studio 2012 p.165 


Q120. - (Topic 3) 

You are the lead developer and architect of a development team that develops line of business (LOB) applications. 

You need to define an architectural design process for the LOB applications. 

Which three architectural goals and principles should you adopt? (Each correct answer presents a complete solution. Choose three.) 

A. Build to change, instead of building to last. 

B. Model to analyze and reduce risk. 

C. Consider the team velocity. 

D. Use models and visualizations as a communication and collaboration tool. 

E. Baseline the architecture to ensure consistency and minimize deviation. 

Answer: A,B,D 

Explanation: Consider the following key principles when designing your architecture: Build to change instead of building to last. Consider how the application may need to change over time to address new requirements and challenges, and build in the flexibility to support this. Model to analyze and reduce risk. Use design tools, modeling systems such as Unified Modeling Language (UML), and visualizations where appropriate to help you capture requirements and architectural and design decisions, and to analyze their impact. However, do not formalize the model to the extent that it suppresses the capability to iterate and adapt the design easily. Use models and visualizations as a communication and collaboration tool. Efficient communication of the design, the decisions you make, and ongoing changes to the design, is critical to good architecture. Use models, views, and other visualizations of the architecture to communicate and share your design efficiently with all the stakeholders, and to enable rapid communication of changes to the design. Identify key engineering decisions. Use the information in this guide to understand the key engineering decisions and the areas where mistakes are most often made. Invest in getting these key decisions right the first time so that the design is more flexible and less likely to be broken by changes. 

http://msdn.microsoft.com/en-us/library/ee658098.aspx