When it comes to CompTIA CompTIA certification exam, almost all of IT aspirants are excited but stressed. As the CompTIA PK0-003 certification is their particular dream yet they have wonderful difficulty in obtaining it without having any support. If you are normally the one who features no notion to put together for the CompTIA PK0-003 exam, Ucertify.org is the best position you should visit. Each of our CompTIA PK0-003 exam dumps are high-quality along with great important which can assure you a new passing score. If you put together for the CompTIA PK0-003 genuine exam with each of our products phase by phase, you will help make full good results. You will be very proud that you have got your CompTIA CompTIA PK0-003 certification. It can additionally lay a good foundation to your career inside IT world.

2021 Dec comptia project+ study guide pk0-003 download:

Q81. - (Topic 3) 

Once a change request has been approved by the Change Control Board, which of the following should the project manager do FIRST? 

A. Request additional funding 

B. Perform an impact analysis 

C. Update the project plan 

D. Inform the project team 

Answer: C


Q82. - (Topic 1) 

The customer has agreed to pay 20% more for the project deliverable if it can be turned over to them in four weeks. The project manager has the team members to complete the project, but is having difficulty procuring enough material from a vendor. The project manager agrees to pay 5% more for the material if complete shipment can be made within a week. This is an example of which of the following risk response strategies? 

A. Transferring 

B. Enhancing 

C. Sharing 

D. Exploiting 

Answer:


Q83. - (Topic 1) 

In a project kick-off meeting, the project manager does which of the following? 

A. Discusses pending change requests 

B. Obtains approval on the budget 

C. Receives buy in from the stakeholders 

D. Reviews the project goals 

Answer:


Q84. - (Topic 1) 

A change request has been authorized to decrease the amount of time the project team has to hand over the deliverable to the customer. The project manager has decided to crash the schedule to accommodate the change. Which of the following will MOST likely occur? 

A. The risk of the project will decrease. 

B. The quality of the deliverable will increase. 

C. The cost of the project will increase. 

D. The scope of the project will decrease. 

Answer:


Q85. - (Topic 3) 

As a part of quality control, a project manager has been monitoring work performance and analyzing information which has indicated variances to the control limits. Which of the following is the NEXT step the project manager should take? 

A. Implement changes to resolve variances 

B. Make the sponsor aware of variances 

C. Meet with the key stakeholders to discuss variances 

D. Generate a change request outlining the variances 

Answer:


Up to the immediate present pk0-003 exam questions:

Q86. - (Topic 3) 

Which of the following would MOST likely be found in the quality management plan? (Select TWO). 

A. Resource quality policies 

B. Quality assurance process description 

C. Risk register 

D. Frequency of quality measurement 

E. Manufacturing specification details 

F. Quality cost calculations 

Answer: B,D 


Q87. - (Topic 2) 

A project manager wants to ensure the project maintains funding and satisfies the intent of the project. Which of the following functions within the communication plan can reduce scope creep? 

A. Implementing change requests 

B. Periodically updating stakeholder 

C. Updating risk register with changes 

D. Analyzing performance information 

Answer:


Q88. - (Topic 1) 

Which of the following would use the WBS to aid in the creation of the cost estimate? A. Analogous 

B. Top down 

C. Parametric 

D. Bottom up 

Answer:


Q89. - (Topic 2) 

A software development project just went live and the operations team is now using the software. However, the operations team is having a significant number of difficulties operating the software. Which of the following is the MOST likely cause of this situation? 

A. Poor transition plan 

B. Poor lessons learned 

C. Poor scope analysis 

D. Poor quality assurance 

Answer:


Q90. - (Topic 3) 

During which of the following process groups is the project charter developed? 

A. Pre-project setup 

B. Project execution 

C. Project planning 

D. Project control 

Answer: