★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PK0-003 Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/PK0-003-dumps.html


Exam Code: PK0-003 (Practice Exam Latest Test Questions VCE PDF)
Exam Name: CompTIA Project+ (2009)
Certification Provider: CompTIA
Free Today! Guaranteed Training- Pass PK0-003 Exam.

2021 Jan pk0-003 comptia project+:

Q161. - (Topic 2) 

The project manager has noticed that five people have completed parts of the project one week ahead of schedule. The project manager decides to use those five people on a different project to ensure an early completion. This is an example of which of the following? 

A. Crashing 

B. Optimizing 

C. Smoothing 

D. Fast tracking 

Answer:


Q162. - (Topic 1) 

Which of the following risk responses is taking place when there is a design change to reduce the scope of the product? 

A. Transfer 

B. Sharing 

C. Acceptance 

D. Avoidance 

Answer:


Q163. - (Topic 3) 

When creating a network diagram, the project manager identifies a relationship between tasks A, B, and C, wherein A must start before B, but B and C may be started at the same time. In this scenario, A is BEST defined as a: 

A. start to start dependency type. 

B. successor to C. 

C. predecessor to B. 

D. finish to start dependency type. 

Answer:


Q164. - (Topic 2) 

Which of the following techniques provides the MOST positive outcomes to conflict? (Select THREE). 

A. Forcing 

B. Smoothing 

C. Influencing 

D. Negotiating 

E. Avoiding 

F. Convincing 

G. Socializing 

H. Compromising 

I. Confronting 

Answer: B,D,H 


Q165. - (Topic 3) 

A project manager has been working on a project for several months and the final deliverable has just been accepted by the customer. The project team is already preparing for transition to future projects, and the project manager drafts a memo reminding the project team that there are a few more tasks to complete before the team is released. The project manager is MOST likely to address which of the following tasks in the memo? (Select TWO). 

A. Validating the project charter 

B. Recognizing the project sponsor 

C. Hosting a lessons-learned event 

D. Developing the risk register 

E. Developing final cost reports 

Answer: C,E 


Replace pk0-003 exam cost:

Q166. - (Topic 3) 

A customer has requested a change order to add functionality to the product being developed. Which of the following is MOST likely to occur? 

A. Scope will decrease 

B. Quality will increase 

C. Schedule will decrease 

D. Cost will increase 

Answer:


Q167. - (Topic 3) 

A project manager is leading a discovery session involving a quality problem discovered in the manufacturing process for a time-sensitive product. In an effort to expedite the process of resolving quality control issues the team would like to focus on improvements that would result in the greatest positive impact to the quality of the product. A data set has been collected over time and is ready for use by the project team. Which of the following graphical data tools would be MOST appropriate to help the project team achieve its stated goals? 

A. Pareto chart 

B. Delphi model 

C. Run chart 

D. Histogram 

E. Ishikawa diagram 

Answer:


Q168. - (Topic 3) 

Which of the following are included in a risk register? (Select TWO). 

A. Project risk responses 

B. Identified risks 

C. Major milestones 

D. Risk analysis tools 

E. Risk control board members 

Answer: A,B 


Q169. - (Topic 1) 

A project baseline should be captured when the: 

A. project manager is satisfied with the project tasks and risks associated. 

B. sponsor is ready for work to begin and conducts a kick-off meeting. 

C. schedule is fully developed with activity names, durations, dependencies, and costs. 

D. WBS and WBS dictionary have been defined and agreed upon. 

Answer:


Q170. - (Topic 2) 

Which of the following is the main purpose of a work breakdown structure? 

A. To decompose the list of deliverables 

B. To identify key stakeholders and their influence 

C. To assign resources to activities 

D. To determine total project duration 

Answer: