★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PMI-001 Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/PMI-001-dumps.html


The PMI PMI-001 practice questions and also answers contain the complete and comprehensive information points. The PMI PMI-001 exam dumps are summarized and also compiled by Exambibles professional team. What you need to accomplish is only sit at home and also download our PMI PMI test engine. Examine the entire PMI PMI-001 practice materials meticulously and diligently. That they must be a fantastic help for that PMI PMI-001 exam preparation. Start before and get certified before and easier.

2021 Nov testking pmi-001:

Q341. Who provides the inputs for the original estimates of activity durations for tasks on the project plan? 

A. Project sponsor 

B. Project manager 

C. Person responsible for project scheduling 

D. Person who is most familiar with the task 

Answer:


Q342. Which cost estimate technique includes contingencies to account for cost uncertainty? 

A. Vendor bid analysis 

B. Three-point estimates 

C. Parametric estimating 

D. Reserve analysis 

Answer:


Q343. What happens to a stakeholder's project influence over time? 

A. Increases 

B. Decreases 

C. Stays the same 

D. Has no bearing 

Answer:


Q344. The scope management plan is a subsidiary of which project document? 

A. Schedule management plan 

B. Project management plan 

C. Quality management plan 

D. Resource management plan 

Answer:


Q345. Project Stakeholder Management focuses on: 

A. project staff assignments 

B. project tea m acquisition 

C. managing conflicting interests 

D. communication methods 

Answer:


Renew phytomedics pmi-001:

Q346. Which tool or technique is used in Close Procurements? 

A. Contract plan 

B. Procurement plan 

C. Closure process 

D. Procurement audits 

Answer:


Q347. Scope verification is PRIMARILY concerned with which of the following? 

A. Acceptance of the work deliverables. 

B. Accuracy of the work deliverables. 

C. Approval of the scope statement. 

D. Accuracy of the work breakdown structure. 

Answer:


Q348. A large portion of a projects budget is typically expended on the processes in which 

Process Group? 

A. Executing 

B. Planning 

C. Monitoring and Controlling 

D. Closing 

Answer:


Q349. Outputs of the Control Communications process include: 

A. expert judgment and change requests. 

B. work performance information and change requests. 

C. organizational process asset updates and an issue log. 

D. project management plan updates and an issue log. 

Answer:


Q350. The scope management plan and scope baseline are contained in: 

A. organizational process assets 

B. a requirements traceability matrix 

C. the project charter 

D. theproject management plan 

Answer: