★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PMI-001 Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/PMI-001-dumps.html


It is impossible to pass PMI PMI-001 exam without any help in the short term. Come to Actualtests soon and find the most advanced, correct and guaranteed PMI PMI-001 practice questions. You will get a surprising result by our Most up-to-date Project Management Professional practice guides.

2021 Feb ca0-001 vs pmi-002:

Q501. Which type of chart is a graphic representation of a process showing the relationships among process steps? 

A. Control 

B. Bar 

C. Flow 

D. Pareto 

Answer:


Q502. Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially? 

A. Crashing 

B. Fast tracking 

C. Leads and lags adjustment 

D. Parallel task development 

Answer:


Q503. The following is a network diagram for a project. 

The critical path for the project is how many days in duration? 

A. 10 

B. 12 

C. 14 

D. 17 

Answer:


Q504. Which Project Time Management process includes bottom-up estimating as a tool or technique? 

A. Estimate Activity Resources 

B. Sequence Activities 

C. Estimate Activity Durations 

D. Develop Schedule 

Answer:


Q505. Which type of team can be defined as a group of people with a shared goal who fulfill their roles although spending little or no time meeting face to face? 

A. Co-location team 

B. Virtual team 

C. Departmental team 

D. Consultant team 

Answer:


Avant-garde pmi-001 questions & answers:

Q506. The milestone list is an input to which process from the Planning Process Group? 

A. Define Activities 

B. Estimate Activity Durations 

C. Estimate Activity Resources 

D. Sequence Activities 

Answer:


Q507. A graphic display of project team members and their reporting relationships is known as a: 

A. Resource calendar. 

B. Project organization chart. 

C. Resource breakdown structure (RBS). 

D. Responsibility assignment matrix (RAM). 

Answer:


Q508. Which of the following is an output of the Plan Quality process? 

A. Project document update 

B. Control chart 

C. Cost performance baseline 

D. Organizational process asset update 

Answer:


Q509. Which element does a project charter contain? 

A. Management reserves 

B. Work breakdown structure 

C. Stakeholder list 

D. Stakeholder register 

Answer:


Q510. Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area? 

A. Project Time Management 

B. Project Cost Management 

C. Project Scope Management 

D. Project Human Resource Management 

Answer: