★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PMI-001 Exam Dumps (PDF & VCE):
Available on: https://www.certleader.com/PMI-001-dumps.html


Act now and download your PMI PMI-001 test today! Do not waste time for the worthless PMI PMI-001 tutorials. Download Regenerate PMI Project Management Professional exam with real questions and answers and begin to learn PMI PMI-001 with a classic professional.

2021 Nov phytomedics pmi-001:

Q291. The process of developing a detailed description of the project and product is known as: 

A. Create WBS. 

B. Verify Scope. 

C. Collect Requirements. 

D. Define Scope. 

Answer:


Q292. Which process involves aggregating the estimated costs of the individual schedule activities or work packages? 

A. Estimate Costs 

B. Estimate Activity Resources 

C. Control Costs 

D. Determine Budget 

Answer:


Q293. The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group? 

A. Initiating 

B. Planning 

C. Executing 

D. Monitoring and Controlling 

Answer:


Q294. What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)? 

A. 0.45 

B. 0.56 

C. 0.70 

D. 1.36 

Answer:


Q295. Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions? 

A. Inspection 

B. Quality audits 

C. Design of experiments 

D. Root cause analysis 

Answer:


Renewal examcollection pmi-001:

Q296. When sequencing activities, what does the common acronym FF stand for? 

A. Fixed Fee 

B. Free Float 

C. Fixed Finish 

D. Finish-to-Finish 

Answer:


Q297. What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)? 

A. 0.03 

B. 0.06 

C. 0.10 

D. 0.50 

Answer:


Q298. Which tool or technique is used to manage change requests and the resulting decisions? 

A. Change control tools 

B. Expert judgment 

C. Delphi technique 

D. Change log 

Answer:


Q299. The Perform Quality Assurance process occurs in which Process Group? 

A. Executing 

B. Monitoring and Controlling 

C. Initiating 

D. Planning 

Answer:


Q300. At the end of the project, what will be the value of SV? 

A. Positive 

B. Zero 

C. Negative 

D. Greater than one 

Answer: